Project Management · Tisch — Wing B

Schedule of Values

BID-1247 · FW #31247

The financial backbone of the Wing B millwork package — 15 G703 lines carrying $1,415,200, from shop drawings to final punch. Change orders amend it, every requisition bills against it, and the field earns it line by line.

Original contract sum

$1,385,000

13 base lines · NTP Jan 19, 2026

Executed change orders

+$30,200

2 executed · +$18,750 pending

Revised contract to date

$1,415,200

BID-1247 · FW #31247

Contract complete

66.1%

$936,080 earned to date

AIA G702/G703 · Application No. 4

Continuation sheet

Cumulative position through the period ending May 31, 2026 — thirteen base lines from the awarded estimate, two executed change-order adjustments, one ledger.

  • General Conditions / Mobilization

    Scheduled Value (C)
    $48,000
    % (G ÷ C)
    90%
    Earned to Date (G)
    $43,200
    Balance to Finish (C − G)
    $4,800
  • Shop Drawings & Engineering

    Scheduled Value (C)
    $62,000
    % (G ÷ C)
    100%
    Earned to Date (G)
    $62,000
    Balance to Finish (C − G)
    $0
  • Plastic-Laminate Casework — Level 2

    Scheduled Value (C)
    $186,000
    % (G ÷ C)
    95%
    Earned to Date (G)
    $176,700
    Balance to Finish (C − G)
    $9,300
  • Plastic-Laminate Casework — Level 3

    Scheduled Value (C)
    $174,000
    % (G ÷ C)
    85%
    Earned to Date (G)
    $147,900
    Balance to Finish (C − G)
    $26,100
  • Wood Veneer Paneling — Lobby & Screening Room

    Scheduled Value (C)
    $228,000
    % (G ÷ C)
    60%
    Earned to Date (G)
    $136,800
    Balance to Finish (C − G)
    $91,200
  • Reception Desks (2) — Solid Surface

    Scheduled Value (C)
    $96,000
    % (G ÷ C)
    40%
    Earned to Date (G)
    $38,400
    Balance to Finish (C − G)
    $57,600
  • Solid-Surface Countertops

    Scheduled Value (C)
    $118,000
    % (G ÷ C)
    55%
    Earned to Date (G)
    $64,900
    Balance to Finish (C − G)
    $53,100
  • Window Stools & Sills

    Scheduled Value (C)
    $54,000
    % (G ÷ C)
    30%
    Earned to Date (G)
    $16,200
    Balance to Finish (C − G)
    $37,800
  • Standing & Running Trim

    Scheduled Value (C)
    $87,000
    % (G ÷ C)
    70%
    Earned to Date (G)
    $60,900
    Balance to Finish (C − G)
    $26,100
  • Blum Hardware & Accessories

    Scheduled Value (C)
    $44,000
    % (G ÷ C)
    65%
    Earned to Date (G)
    $28,600
    Balance to Finish (C − G)
    $15,400
  • Fire-Treated Blocking & Backing

    Scheduled Value (C)
    $36,000
    % (G ÷ C)
    100%
    Earned to Date (G)
    $36,000
    Balance to Finish (C − G)
    $0
  • Installation Labor — Levels 2–3

    Scheduled Value (C)
    $214,000
    % (G ÷ C)
    52%
    Earned to Date (G)
    $111,280
    Balance to Finish (C − G)
    $102,720
  • Final Adjust, Punch & Closeout

    Scheduled Value (C)
    $38,000
    % (G ÷ C)
    0%
    Earned to Date (G)
    $0
    Balance to Finish (C − G)
    $38,000
  • CO-001 — AV Credenza Millwork, Room B-214 (add)

    Added by CO-001 · Executed Apr 10, 2026

    Scheduled Value (C)
    $42,500
    % (G ÷ C)
    60%
    Earned to Date (G)
    $25,500
    Balance to Finish (C − G)
    $17,000
  • CO-003 — Delete Window Stools, Level 3 Corridor (credit)

    Credit per CO-003 · Executed Apr 18, 2026

    Scheduled Value (C)
    ($12,300)
    % (G ÷ C)
    100%
    Earned to Date (G)
    ($12,300)
    Balance to Finish (C − G)
    $0
  • Contract totals · 15 lines
    Scheduled Value (C)
    $1,415,200
    % (G ÷ C)
    66.1%
    Earned to Date (G)
    $936,080
    Balance to Finish (C − G)
    $479,120

G702 · Application No. 4

Retainage & billing position

Retainage held10% of work completed to date
$93,608
Payments received to dateApplications #1–#3 · certified & paid
$469,233
Materials presently storedG703 column F — nothing billed ahead of installation
$0
Current payment dueSubmittedREQ-004 · period ending May 31, 2026 · submitted Jun 02, 2026
$373,239
Reconcile against pay applications

Contract value · original → revised

Change-order reconciliation

Original contract sum13 base lines · awarded schedule
$1,385,000
AV Credenza Millwork — Room B-214CO-001 · Executed Apr 10, 2026 · Line 14
+$42,500
Delete Window Stools — Level 3 CorridorCO-003 · Executed Apr 18, 2026 · Line 15
($12,300)
Revised contract to date
$1,415,200
Revised Reception Desk — Solid-Surface Profile per ASI-07PendingCO-002 · Submitted May 18, 2026 · per ASI-07 · joins the schedule on execution
+$18,750
Full change-order log

How this connects

Data flows from Fieldwire job #31247 (Sheets, Tasks, Progress photos) through the Fieldwire bridge into the SOV Workflow skill, which produces G703 continuation sheet (.xlsx).

Demo data — task completion on FW #31247 will drive Work Completed (G ÷ C) line by line once the Fieldwire bridge automation ships in the integration phase.

Project
Tisch School of the Arts — Wing B Renovation
Drawn by
IM
Scale
NTS
Date
Jun 02, 2026
Rev
Δ 2
Sheet no.
G-703