Project Management · Tisch — Wing B
What the work has earned.
BID-1247 · FW #31247
Four requisitions against the Wing B millwork contract — G702/G703 style, billed on cumulative percent complete, 10% retainage held to closeout. App #4 is in front of Hunter Roberts now.
Total earned to date
$936,080
Retainage held
$93,608
Paid to date
$469,233
Current payment due
$373,239
01 · Application index
Requisitions to date
Every application this contract has billed — current first. Apps #1–2 ran against the original 13-line schedule; #3–4 carry the CO adjustment lines.
REQ-004 · Pay App #4
Application & certificate for payment
May 01 – May 31, 2026
- Work this period
- $414,710
- Completed to date
- $936,080
- Retainage @ 10%
- $93,608
Current payment due
$373,239
submitted Jun 02, 2026
REQ-003 · Pay App #3
Application & certificate for payment
Apr 01 – Apr 30, 2026
- Work this period
- $290,220
- Completed to date
- $521,370
- Retainage @ 10%
- $52,137
Current payment due
$261,198
submitted May 05, 2026
REQ-002 · Pay App #2
Application & certificate for payment
Mar 01 – Mar 31, 2026
- Work this period
- $156,950
- Completed to date
- $231,150
- Retainage @ 10%
- $23,115
Current payment due
$141,255
submitted Apr 03, 2026
REQ-001 · Pay App #1
Application & certificate for payment
Jan 19 – Feb 28, 2026
- Work this period
- $74,200
- Completed to date
- $74,200
- Retainage @ 10%
- $7,420
Current payment due
$66,780
submitted Mar 04, 2026
02 · REQ-004 · Pay App #4
G703 continuation sheet
Period May 01, 2026 – May 31, 2026. Fifteen lines including CO adjustments L14/L15 — the CO-003 credit bills at 100% from approval and renders in parentheses. No materials presently stored this period.
- General Conditions / Mobilization
- Item
- 1
- This period
- $4,800
- %
- 90%
- Total to date
- $43,200
- Shop Drawings & Engineering
- Item
- 2
- This period
- $0
- %
- 100%
- Total to date
- $62,000
- Plastic-Laminate Casework — Level 2
- Item
- 3
- This period
- $46,500
- %
- 95%
- Total to date
- $176,700
- Plastic-Laminate Casework — Level 3
- Item
- 4
- This period
- $52,200
- %
- 85%
- Total to date
- $147,900
- Wood Veneer Paneling — Lobby & Screening Room
- Item
- 5
- This period
- $79,800
- %
- 60%
- Total to date
- $136,800
- Reception Desks (2) — Solid Surface
- Item
- 6
- This period
- $38,400
- %
- 40%
- Total to date
- $38,400
- Solid-Surface Countertops
- Item
- 7
- This period
- $41,300
- %
- 55%
- Total to date
- $64,900
- Window Stools & Sills
- Item
- 8
- This period
- $16,200
- %
- 30%
- Total to date
- $16,200
- Standing & Running Trim
- Item
- 9
- This period
- $26,100
- %
- 70%
- Total to date
- $60,900
- Blum Hardware & Accessories
- Item
- 10
- This period
- $15,400
- %
- 65%
- Total to date
- $28,600
- Fire-Treated Blocking & Backing
- Item
- 11
- This period
- $0
- %
- 100%
- Total to date
- $36,000
- Installation Labor — Levels 2–3
- Item
- 12
- This period
- $72,760
- %
- 52%
- Total to date
- $111,280
- Final Adjust, Punch & Closeout
- Item
- 13
- This period
- $0
- %
- 0%
- Total to date
- $0
- CO-001 — AV Credenza Millwork, Room B-214 (add)
- Item
- 14
- This period
- $21,250
- %
- 60%
- Total to date
- $25,500
- CO-003 — Delete Window Stools, Level 3 Corridor (credit)
- Item
- 15
- This period
- $0
- %
- 100%
- Total to date
- ($12,300)
03 · Summary & certification
The G702 face
The nine summary lines foot to the continuation sheet above; the certification carries the PM's signature until the architect certifies.
G702 · Application summary
Application #4 — contract status
- 1.Original contract sum
- $1,385,000
- 2.Net change by approved change orders
- +$30,200
- 3.Contract sum to date
- $1,415,200
- 4.Total completed & stored to date
- $936,080
- 5.Retainage — 10% of completed work
- $93,608
- 6.Total earned less retainage
- $842,472
- 7.Less previous certificates for payment
- $469,233
- 8.Current payment due
- $373,239
- 9.Balance to finish, incl. retainage
- $479,120
Retainage
10% held → released at closeout
Hunter Roberts holds 10 cents of every certified dollar until the package closes out. The held balance returns on the final requisition — punch list complete, attic stock delivered, closeout documents accepted.
- Rate
- 10% of work completed
- Held to date
- $93,608
- Release
- Final requisition at closeout
- Substantial completion
- Aug 28, 2026
G702 · Certification
Certified by
The undersigned Contractor certifies that, to the best of the Contractor’s knowledge, the Work covered by this Application for Payment has been completed in accordance with the Contract Documents and that the current payment shown herein is now due.
Marco Delgado
Contractor — Elli NY Design Corp
Marco Delgado, Project Manager
Jun 02, 2026
Architect — Studio Marek Architecture
Avery Lin, Project Architect
How this connects
Data flows from SOV + Fieldwire progress (% complete, Daily logs, Photos) through the Fieldwire bridge into the Pay Application Workflow skill, which produces G702/G703 package (.pdf).
Demo data — the bridge reads task percent complete, daily logs, and photo evidence from FW #31247 to draft each line's progress against the SOV. Automation ships in the integration phase; the PM reviews and submits every requisition.