Skip to content

Hub

Demo data

Project Management · Tisch — Wing B

What the work has earned.

BID-1247 · FW #31247

Four requisitions against the Wing B millwork contract — G702/G703 style, billed on cumulative percent complete, 10% retainage held to closeout. App #4 is in front of Hunter Roberts now.

Total earned to date

$936,080

66.1% of $1,415,200 revised contract

Retainage held

$93,608

10% of completed work — released at closeout

Paid to date

$469,233

Apps #1–3 certified & paid

Current payment due

$373,239

App #4 · submitted Jun 02, 2026

01 · Application index

Requisitions to date

Every application this contract has billed — current first. Apps #1–2 ran against the original 13-line schedule; #3–4 carry the CO adjustment lines.

REQ-004 · Pay App #4

SubmittedCurrent

Application & certificate for payment

May 01 – May 31, 2026

Work this period
$414,710
Completed to date
$936,080
Retainage @ 10%
$93,608

Current payment due

$373,239

submitted Jun 02, 2026

REQ-003 · Pay App #3

Paid

Application & certificate for payment

Apr 01 – Apr 30, 2026

Work this period
$290,220
Completed to date
$521,370
Retainage @ 10%
$52,137

Current payment due

$261,198

submitted May 05, 2026

REQ-002 · Pay App #2

Paid

Application & certificate for payment

Mar 01 – Mar 31, 2026

Work this period
$156,950
Completed to date
$231,150
Retainage @ 10%
$23,115

Current payment due

$141,255

submitted Apr 03, 2026

REQ-001 · Pay App #1

Paid

Application & certificate for payment

Jan 19 – Feb 28, 2026

Work this period
$74,200
Completed to date
$74,200
Retainage @ 10%
$7,420

Current payment due

$66,780

submitted Mar 04, 2026

02 · REQ-004 · Pay App #4

G703 continuation sheet

Period May 01, 2026 May 31, 2026. Fifteen lines including CO adjustments L14/L15 — the CO-003 credit bills at 100% from approval and renders in parentheses. No materials presently stored this period.

  • General Conditions / Mobilization
    Item
    1
    This period
    $4,800
    %
    90%
    Total to date
    $43,200
  • Shop Drawings & Engineering
    Item
    2
    This period
    $0
    %
    100%
    Total to date
    $62,000
  • Plastic-Laminate Casework — Level 2
    Item
    3
    This period
    $46,500
    %
    95%
    Total to date
    $176,700
  • Plastic-Laminate Casework — Level 3
    Item
    4
    This period
    $52,200
    %
    85%
    Total to date
    $147,900
  • Wood Veneer Paneling — Lobby & Screening Room
    Item
    5
    This period
    $79,800
    %
    60%
    Total to date
    $136,800
  • Reception Desks (2) — Solid Surface
    Item
    6
    This period
    $38,400
    %
    40%
    Total to date
    $38,400
  • Solid-Surface Countertops
    Item
    7
    This period
    $41,300
    %
    55%
    Total to date
    $64,900
  • Window Stools & Sills
    Item
    8
    This period
    $16,200
    %
    30%
    Total to date
    $16,200
  • Standing & Running Trim
    Item
    9
    This period
    $26,100
    %
    70%
    Total to date
    $60,900
  • Blum Hardware & Accessories
    Item
    10
    This period
    $15,400
    %
    65%
    Total to date
    $28,600
  • Fire-Treated Blocking & Backing
    Item
    11
    This period
    $0
    %
    100%
    Total to date
    $36,000
  • Installation Labor — Levels 2–3
    Item
    12
    This period
    $72,760
    %
    52%
    Total to date
    $111,280
  • Final Adjust, Punch & Closeout
    Item
    13
    This period
    $0
    %
    0%
    Total to date
    $0
  • CO-001 — AV Credenza Millwork, Room B-214 (add)
    Item
    14
    This period
    $21,250
    %
    60%
    Total to date
    $25,500
  • CO-003 — Delete Window Stools, Level 3 Corridor (credit)
    Item
    15
    This period
    $0
    %
    100%
    Total to date
    ($12,300)
Scheduled value
$1,415,200
Previous applications
$521,370
This period
$414,710
Materials stored
$0
Total completed
$936,080
Balance to finish
$479,120
Retainage
$93,608

03 · Summary & certification

The G702 face

The nine summary lines foot to the continuation sheet above; the certification carries the PM's signature until the architect certifies.

G702 · Application summary

Application #4 — contract status

1.Original contract sum
$1,385,000
2.Net change by approved change orders
+$30,200
3.Contract sum to date
$1,415,200
4.Total completed & stored to date
$936,080
5.Retainage — 10% of completed work
$93,608
6.Total earned less retainage
$842,472
7.Less previous certificates for payment
$469,233
8.Current payment due
$373,239
9.Balance to finish, incl. retainage
$479,120

Materials presently stored: $0 — modeled as zero; millwork bills on placed work.

CO-002 (+$18,750) is pending — excluded from the contract sum until approved.

Retainage

10% held → released at closeout

Hunter Roberts holds 10 cents of every certified dollar until the package closes out. The held balance returns on the final requisition — punch list complete, attic stock delivered, closeout documents accepted.

Rate
10% of work completed
Held to date
$93,608
Release
Final requisition at closeout
Substantial completion
Aug 28, 2026

G702 · Certification

Certified by

SpecimenDemo data

The undersigned Contractor certifies that, to the best of the Contractor’s knowledge, the Work covered by this Application for Payment has been completed in accordance with the Contract Documents and that the current payment shown herein is now due.

Marco Delgado

Contractor — Elli NY Design Corp

Marco Delgado, Project Manager

Jun 02, 2026

Architect — Studio Marek Architecture

Avery Lin, Project Architect

Pendingcertificate for $373,239

Specimen rendering — the executed G702/G703 package (.pdf) is generated by the Pay Application Workflow skill in the integration phase. Nothing is signed or transmitted from this screen.

How this connects

Data flows from SOV + Fieldwire progress (% complete, Daily logs, Photos) through the Fieldwire bridge into the Pay Application Workflow skill, which produces G702/G703 package (.pdf).

Demo data — the bridge reads task percent complete, daily logs, and photo evidence from FW #31247 to draft each line's progress against the SOV. Automation ships in the integration phase; the PM reviews and submits every requisition.

Project
Tisch School of the Arts — Wing B Renovation
Drawn by
MD
Date
Jun 02, 2026
Rev
Δ 0
Sheet no.
G702-04