Project Management · Tisch — Wing B

Change orders

BID-1247 · FW #31247

Every priced change against the millwork contract, from originating directive to executed copy. Approved changes move the G703; pending pricing stays outside the contract sum until Hunter Roberts returns signatures.

Contract position

AIA G702 · Lines 1–3

Original contract

G702 line 1

$1,385,000

Approved changes

G702 line 2 · net

+$30,200

Revised contract

G702 line 3 · to date

$1,415,200

Pending · not in sum

CO-002 · with the GC

+$18,750

Net change by change orders: CO-001 add and CO-003 credit, both executed and carried on the G703. Executed changes add +5 days to the schedule; CO-002 carries +8 days and joins the contract sum only when the countersigned copy returns. Credits render in parentheses.

Register · 3 change orders

The register

2 executed1 pending

Each CO carries its origin, its schedule impact, and the schedule-of-values line it moves — the same lineage the Change Order Workflow skill will assemble from Fieldwire.

CO-001from ASI-04Executed

AV Credenza Millwork — Room B-214

Add plastic-laminate AV credenza with ventilated equipment bays and Blum soft-close hardware per ASI-04. Includes solid-surface top and fire-treated blocking.

Submitted
Mar 24, 2026
Executed
Apr 10, 2026
Origin ref
ASI-04
Schedule
+5 days

Change to contract sum

+$42,500Add

G703 lines moved

SOV L14 · Item 14

ExecutedApr 10, 2026
CO-002from ASI-07Pending

Revised Reception Desk — Solid-Surface Profile per ASI-07

Re-fabricate main reception desk front per revised radius profile and integral signage reveal issued under ASI-07. Pricing submitted; awaiting GC approval.

Submitted
May 18, 2026
GC decision
In Hunter Roberts' court
Origin ref
ASI-07
Schedule
+8 days

Change to contract sum

+$18,750Add

G703 lines moved

Joins the G703 as a new line on execution — held outside the schedule until then.

Awaiting GC executed copy. Pricing went to Hunter Roberts on May 18, 2026 — the +$18,750 stays out of the contract sum, and off the G703, until the countersigned CO comes back.

CO-003from RFI-003Executed

Delete Window Stools — Level 3 Corridor

Credit for deletion of solid-surface window stools at Level 3 corridor; changed to GC-furnished stone sills per RFI-003 resolution.

Submitted
Apr 06, 2026
Executed
Apr 18, 2026
Origin ref
RFI-003
Schedule

Change to contract sum

($12,300)Credit

G703 lines moved

SOV L15 · Item 15

ExecutedApr 18, 2026

How this connects

Data flows from Fieldwire job #31247 (Field directives, T&M tickets, Photos) through the Fieldwire bridge into the Change Order Workflow skill, which produces PCO package (.pdf) + updated SOV.

Demo data — the bridge automation that gathers field directives, T&M tickets, and photo backup from FW #31247 into a priced PCO package ships in the integration phase. Until then, this register is kept by hand.

Project
Tisch School of the Arts — Wing B Renovation
Drawn by
MD
Scale
NTS
Date
May 18, 2026
Rev
Δ 3
Sheet no.
CO-LOG