Project Management · Tisch — Wing B
Submittals
BID-1247 · FW #31247
Eight packages cover the millwork scope — AWI Premium casework shop drawings, Wilsonart and rift white oak veneer samples, Blum hardware data. Each one moves Ellicorp → Hunter Roberts → Studio Marek and back.
01 · Standing
Where the log stands
Lifecycle across the eight packages, and who holds the action today.
Packages on the log
8
Approved
5 / 8
In court
3
Lifecycle
8 packages
Register composition: 3 Approved, 2 Approved as Noted, 1 In Review, 1 Submitted, 1 Revise & Resubmit.
- Approved3
- Approved as Noted2
- In Review1
- Submitted1
- Revise & Resubmit1
Ball in court
as of Jun 11, 2026
Ellicorp · Sub
6
Hunter Roberts · GC
1
Studio Marek · Architect
1
Returned packages rest in Ellicorp’s court — the live action sits below.
SUB-004
Wood Veneer Flitch Samples — Rift White Oak
with Studio Marek · held 30d
due in 5dSUB-007 R1
Reception Desk Shop Drawings — Solid Surface
with Ellicorp · held 27d
due in 8dSUB-008
Standing & Running Trim Profile Samples
with Hunter Roberts · held 3d
due Jun 29, 2026
02 · Register
The register
Click any package for the full record — review cycle, stamp, and log notes.
| No. | Submittal | Spec | Type | Status | Ball in court | Submitted | Due |
|---|---|---|---|---|---|---|---|
| SUB-001 R1 | 06 41 16 | Shop Drawings | Approved as Noted | Ellicorp | Feb 04, 2026 | Feb 25, 2026 | |
| SUB-002 | 06 41 16 | Samples | Approved | Ellicorp | Feb 11, 2026 | Mar 04, 2026 | |
| SUB-003 | 06 41 16 | Product Data | Approved as Noted | Ellicorp | Feb 18, 2026 | Mar 11, 2026 | |
| SUB-004 | 06 42 16 | Samples | In Review | Architectheld 30d | May 12, 2026 | Jun 16, 2026due in 5d | |
| SUB-005 | 12 36 61 | Product Data | Approved | Ellicorp | Mar 03, 2026 | Mar 24, 2026 | |
| SUB-006 | 06 10 53 | Certificates | Approved | Ellicorp | Mar 12, 2026 | Mar 19, 2026 | |
| SUB-007 R1 | 06 41 16 | Shop Drawings | Revise & Resubmit | Ellicorpheld 27d | Apr 21, 2026 | Jun 19, 2026due in 8d | |
| SUB-008 | 06 22 13 | Samples | Submitted | GCheld 3d | Jun 08, 2026 | Jun 29, 2026 |
- No.
- SUB-001 R1
- Spec
- 06 41 16
- Type
- Shop Drawings
- Status
- Approved as Noted
- Ball in court
- Ellicorp
- Due
- Feb 25, 2026
- No.
- SUB-002
- Spec
- 06 41 16
- Type
- Samples
- Status
- Approved
- Ball in court
- Ellicorp
- Due
- Mar 04, 2026
- No.
- SUB-003
- Spec
- 06 41 16
- Type
- Product Data
- Status
- Approved as Noted
- Ball in court
- Ellicorp
- Due
- Mar 11, 2026
- No.
- SUB-004
- Spec
- 06 42 16
- Type
- Samples
- Status
- In Review
- Ball in court
- Architectheld 30d
- Due
- Jun 16, 2026due in 5d
- No.
- SUB-005
- Spec
- 12 36 61
- Type
- Product Data
- Status
- Approved
- Ball in court
- Ellicorp
- Due
- Mar 24, 2026
- No.
- SUB-006
- Spec
- 06 10 53
- Type
- Certificates
- Status
- Approved
- Ball in court
- Ellicorp
- Due
- Mar 19, 2026
- No.
- SUB-007 R1
- Spec
- 06 41 16
- Type
- Shop Drawings
- Status
- Revise & Resubmit
- Ball in court
- Ellicorpheld 27d
- Due
- Jun 19, 2026due in 8d
- No.
- SUB-008
- Spec
- 06 22 13
- Type
- Samples
- Status
- Submitted
- Ball in court
- GCheld 3d
- Due
- Jun 29, 2026
8 of 8 packages · register as of Jun 11, 2026
How this connects
Data flows from Fieldwire job #31247 (Shop drawings, Hardware schedules, Sample logs) through the Fieldwire bridge into the Submittal Log Workflow skill, which produces Submittal log (.xlsx) + transmittals.
Demo data — the bridge automation that keeps this register in step with Fieldwire ships in the integration phase. Nothing here sends or files itself.