Project Management · Tisch — Wing B

Requests for Information

BID-1247 · FW #31247

Every field question on the millwork package — blocking, field dimensions, finish profiles, Blum hardware — on the record from ask to answer, routed through Hunter Roberts to Studio Marek Architecture.

Open

1

answer due Jun 12, 2026

Answered

4

of 6 on the log

Overdue

0

as of Jun 11, 2026

Avg days to answer

8

across 4 answered

Ball in court · 2 unanswered

Awaiting an answer

Unanswered questions hold shop tickets — chase these first.

RFI-005OpenSchedule impact

Reception Desk — Power/Data Grommet Locations Conflict

Electrical drawing E-201 grommet locations at the main reception desk land within the drawer bank shown on SUB-007. Request revised grommet locations or confirmation to shift drawer bank 6" north.

required Jun 12, 2026 · due tomorrow

RFI-006DraftCost impact

Fire-Rating Requirement — Trim Within Stair B Enclosure

Confirm whether standing-and-running trim within the Stair B enclosure (2-hr rated) must be fire-treated material or may be field-finished poplar with intumescent coating per spec 06 22 13 alternates.

not issued · required Jun 25, 2026 · due in 14 days

Register · 6 on the log

RFI log

Unanswered items lead; answered follow in numeric order. Select any subject for the full question, the answer on record, and the sheets it cites.

  • RFI
    RFI-005
    Status
    Open
    Answered by
    — with Architect
    Asked
    May 28, 2026
    Answered
    due Jun 12, 2026
  • RFI
    RFI-006
    Status
    Draft
    Answered by
    — with Ellicorp
    Asked
    not issued
    Answered
    due Jun 25, 2026
  • RFI
    RFI-001
    Status
    Answered
    Answered by
    Avery LinStudio Marek Architecture
    Asked
    Feb 23, 2026
    Answered
    Mar 03, 2026
  • RFI
    RFI-002
    Status
    Answered
    Answered by
    Avery LinStudio Marek Architecture
    Asked
    Mar 09, 2026
    Answered
    Mar 17, 2026
  • RFI
    RFI-003
    Status
    Answered
    Answered by
    Avery LinStudio Marek Architecture
    Asked
    Mar 23, 2026
    Answered
    Apr 01, 2026
  • RFI
    RFI-004
    Status
    Answered
    Answered by
    Dana PierceHunter Roberts Construction Group
    Asked
    Apr 13, 2026
    Answered
    Apr 20, 2026

How this connects

Data flows from Fieldwire job #31247 (Tasks, Sheet markups, Photos) through the Fieldwire bridge into the RFI Workflow skill, which produces RFI log (.xlsx) + RFI forms (.pdf).

Demo data — field questions start life as Fieldwire tasks. The bridge carries each task, its sheet markups, and photos into the RFI Workflow skill, which drafts the form and keeps the log current. Automation ships in the integration phase.