Project Management · Tisch — Wing B

The field, day by day.

BID-1247 · FW #31247

5 daily reports from Tomasz Wozniak’s crew — manpower, weather, areas worked, and what actually went in. Synced from Fieldwire each morning; newest first.

Crew-days

35

5 reports · Jun 04, 2026 – Jun 10, 2026

Man-hours logged

280

avg 56 hrs per report

Photos captured

12

synced from FW #31247

Areas active

8

unique work areas this period
Crew on site · by day

Field reports · newest first

The journal

5 reports

Each report as the crew filed it — weather and manpower up top, then the day's installs, deliveries received, and anything flagged.

  1. Jun 10, 2026

    DL-005Latest

    Weather
    Sunny · 75°/60°
    Crew on site
    6 crew
    Hours worked
    48 hrs

    Areas worked

    Level 3 Rooms B-301–B-306Level 2 Punch

    Work performed

    • Set casework rooms B-301 through B-303 (7 units).
    • Started Level 2 punch prep: hardware adjustment, laminate touch-up.
    • Window stool install, Level 2 (eased edge per RFI-003).

    Photos

    2 photos · Fieldwire

    Synced from FW #31247 · FW-31247-DR-05

    P-11
    P-12
  2. Jun 09, 2026

    DL-004

    Weather
    Overcast · 70°/61°
    Crew on site
    8 crew
    Hours worked
    64 hrs

    Areas worked

    LobbyReception Area

    Work performed

    • Continued veneer paneling installation, lobby west wall (sequence-matched flitches).
    • Templated main reception desk location; flagged grommet conflict pending RFI-005.
    • Installed solid-surface tops at Level 2 corridor casework (6 pieces).

    Flagged

    • Reception desk fabrication holds pending RFI-005 answer and ASI-07 / CO-002 approval.

    Photos

    3 photos · Fieldwire

    Synced from FW #31247 · FW-31247-DR-04

    P-08
    P-09
    P-10
  3. Jun 08, 2026

    DL-003

    Weather
    Rain · 72°/64°
    Crew on site
    8 crew
    Hours worked
    64 hrs

    Areas worked

    LobbyScreening Room West Wall

    Work performed

    • Laid out veneer paneling grid, lobby north and east walls.
    • Verified fire-treated blocking at 32" o.c. per RFI-001 — accepted.
    • Installed panel cleats and started first paneling course, lobby north.

    Flagged

    • Loading dock shared with HVAC sub 7–9 AM; veneer delivery shifted to 10 AM.

    Photos

    2 photos · Fieldwire

    Synced from FW #31247 · FW-31247-DR-03

    P-06
    P-07
  4. Jun 05, 2026

    DL-002

    Weather
    Partly cloudy · 81°/66°
    Crew on site
    7 crew
    Hours worked
    56 hrs

    Areas worked

    Level 2 CorridorLevel 3 Staging

    Work performed

    • Completed upper cabinet installation, Level 2 corridor (11 units).
    • Received and staged Level 3 casework delivery — 14 crates, no damage.
    • Installed Blum hinges and adjusted soft-close at completed runs.

    Deliveries received

    • Solid-surface countertops, Level 2 (6 pieces)
    • Level 3 casework, crates 1–14

    Photos

    3 photos · Fieldwire

    Synced from FW #31247 · FW-31247-DR-02

    P-03
    P-04
    P-05
  5. Jun 04, 2026

    DL-001

    Weather
    Sunny · 78°/63°
    Crew on site
    6 crew
    Hours worked
    48 hrs

    Areas worked

    Level 2 CorridorLevel 2 Rooms B-204–B-208

    Work performed

    • Set plastic-laminate base cabinets B-204 through B-206 (9 units).
    • Scribed and installed filler at column C-4 per RFI-002 resolution.
    • Field-verified solid-surface top dims for Level 2 corridor run.

    Photos

    2 photos · Fieldwire

    Synced from FW #31247 · FW-31247-DR-01

    P-01
    P-02

How this connects

Data flows from Fieldwire job #31247 (Daily reports, Photos, Manpower) through the Fieldwire bridge into the Daily Log Workflow skill, which produces Daily log register (.pdf).

Demo data — the Fieldwire bridge will pull daily reports, photos, and manpower from FW #31247 on a schedule. Automation ships in the integration phase.