5 daily reports from Tomasz Wozniak’s crew — manpower, weather, areas worked, and what actually went in. Synced from Fieldwire each morning; newest first.
Crew-days
35
Man-hours logged
280
Photos captured
12
Areas active
8
Field reports · newest first
The journal
Each report as the crew filed it — weather and manpower up top, then the day's installs, deliveries received, and anything flagged.
- Wed06/10No. 05
Jun 10, 2026
DL-005Latest
- Weather
- Sunny · 75°/60°
- Crew on site
- 6 crew
- Hours worked
- 48 hrs
Areas worked
Level 3 Rooms B-301–B-306Level 2 PunchWork performed
- Set casework rooms B-301 through B-303 (7 units).
- Started Level 2 punch prep: hardware adjustment, laminate touch-up.
- Window stool install, Level 2 (eased edge per RFI-003).
- Tue06/09No. 04
Jun 09, 2026
DL-004
- Weather
- Overcast · 70°/61°
- Crew on site
- 8 crew
- Hours worked
- 64 hrs
Areas worked
LobbyReception AreaWork performed
- Continued veneer paneling installation, lobby west wall (sequence-matched flitches).
- Templated main reception desk location; flagged grommet conflict pending RFI-005.
- Installed solid-surface tops at Level 2 corridor casework (6 pieces).
Flagged
- Reception desk fabrication holds pending RFI-005 answer and ASI-07 / CO-002 approval.
- Mon06/08No. 03
Jun 08, 2026
DL-003
- Weather
- Rain · 72°/64°
- Crew on site
- 8 crew
- Hours worked
- 64 hrs
Areas worked
LobbyScreening Room West WallWork performed
- Laid out veneer paneling grid, lobby north and east walls.
- Verified fire-treated blocking at 32" o.c. per RFI-001 — accepted.
- Installed panel cleats and started first paneling course, lobby north.
Flagged
- Loading dock shared with HVAC sub 7–9 AM; veneer delivery shifted to 10 AM.
06/06–06/07 · weekend — no report filed06/06–06/07 · weekend — no report filed
- Fri06/05No. 02
Jun 05, 2026
DL-002
- Weather
- Partly cloudy · 81°/66°
- Crew on site
- 7 crew
- Hours worked
- 56 hrs
Areas worked
Level 2 CorridorLevel 3 StagingWork performed
- Completed upper cabinet installation, Level 2 corridor (11 units).
- Received and staged Level 3 casework delivery — 14 crates, no damage.
- Installed Blum hinges and adjusted soft-close at completed runs.
Deliveries received
- Solid-surface countertops, Level 2 (6 pieces)
- Level 3 casework, crates 1–14
- Thu06/04No. 01
Jun 04, 2026
DL-001
- Weather
- Sunny · 78°/63°
- Crew on site
- 6 crew
- Hours worked
- 48 hrs
Areas worked
Level 2 CorridorLevel 2 Rooms B-204–B-208Work performed
- Set plastic-laminate base cabinets B-204 through B-206 (9 units).
- Scribed and installed filler at column C-4 per RFI-002 resolution.
- Field-verified solid-surface top dims for Level 2 corridor run.